A leading turbine manufacturer’s service team and PRÜFTECHNIK specialists used CentrAlign™ to align a 550 MW steam turbine
The project was completed in just 10 days instead of the usual 20. Eliminating the need for dummy shafts allowed real-time adjustments during alignment and accuracy reached ±0.03 mm, meeting the manufacturer’s strict standards.